Subject to change due to mountain weather, the NSW National Parks and Wildlife Service has given a timetable for hut rebuilds(as at June 2022).

Rest House at Sawyers Hill:       

nearly complete 2022

Harveys/Tantangara:                  

October 2022

Vickery’s prefab:                        

18th July to 11th August 2022 at Tumut

Vickery’s onsite:                         

September, October 2022 (Pending access)

Delaney’s:                                  

November, December 2022, January 2023

Vickery’s alt if too wet- or Bradley/OBriens                  

February, March, April 2023 

Four Mile:                                 

March, April, May 2024

Happy’s:                                    

December 23, January, February 24

Brook’s:                                     

 September, October, November 2023

Bradley/O’Briens                        

September, October, November 2024

Fifteen Mile/Linesmans               

December 24, January, February 25

Round Mountain                         

March, April, May 2025

Please email Megan Bowden, Project Officer Hut Rebuilding Program at This email address is being protected from spambots. You need JavaScript enabled to view it. with any enquiries.