Subject to change due to mountain weather, the NSW National Parks and Wildlife Service has given a timetable for hut rebuilds(as at June 2022).
Rest House at Sawyers Hill:
nearly complete 2022
Harveys/Tantangara:
October 2022
Vickery’s prefab:
18th July to 11th August 2022 at Tumut
Vickery’s onsite:
September, October 2022 (Pending access)
Delaney’s:
November, December 2022, January 2023
Vickery’s alt if too wet- or Bradley/OBriens
February, March, April 2023
Four Mile:
March, April, May 2024
Happy’s:
December 23, January, February 24
Brook’s:
September, October, November 2023
Bradley/O’Briens
September, October, November 2024
Fifteen Mile/Linesmans
December 24, January, February 25
Round Mountain
March, April, May 2025
Please email Megan Bowden, Project Officer Hut Rebuilding Program at This email address is being protected from spambots. You need JavaScript enabled to view it. with any enquiries.